Material Storage

THE TRANSPORTATION COMPANY IS RESPONSIBLE FOR DELIVERING THE COMPONENTS UNDAMAGED.

WHEN THE SHIPMENT IS RECEIVED, CHECK EACH ITEM AGAINST THE PROPER SHIPPING DOCUMENT IF A SHORTAGE IS DISCOVERED, HAVE THE TRANSPORTATION AGENT MAKE A NOTATION ON YOUR BILL.

EXAM YOUR SHIPMENT CAREFULLY FOR DAMAGE IF ANY DAMAGE IS FOUND BE SURE THE AGENT MAKES A DAMAGE NOTE ON THE BILL BEFORE ACCEPTING IT.

IF DAMAGE IS CONCEALED UNTIL CRATING OR PACKING IS REMOVED, CALL YOUR DEALER AT ONCE FOR AN INSPECTION AND OBTAIN AN INSPECTION MEMO COVERING CONCEALED DAMAGE.

  

 

Recommended jobsite storage, &
protection for wall & roof sheeting

1. Block above ground to keep water out.
2. Slope bundles for drainage.
3. Stack sheeting with spacers between bundles.
4. Cover with tarp to protect from the element.
5. Tie down cover ends away from stack to permit
free air movement. Do not wrap under or restrict air movement.

 

Copyright (c) A-Z Technical Bldg. Systems Inc. 01/01/2001